September 3 Go-Live Cutover Calendar

 

Click here to return to the "A" Agencies Cutover main page.

Click here to access HR/Payroll Cutover Tools, Templates and Information.

 

"A" Agencies – September 3 Go Live
Cutover Calendar of Events


Thursday, August 1 – Tuesday, September 3, 2013

Date

Activity

Friday, August 2 SCEIS Ready Room activities and Cutover Kickoff Meeting.
Tuesday, August 13 SCEIS Pre-go-live Ready Room closes. Ready Room activities will re-start on September 3.
Friday, August 16
 
Cutover Start Date
Activities to complete before 6:00 p.m.:
  • Complete validation of organizational structures in Nakisa.
  • Halt or monitor all direct-deposit changes made just before or during the freeze period.
  • Identify all employees to a Work Schedule Rule and Work Periods (IT007).
  • Process outstanding pay actions with effective dates on or before May 16.
  • Resolve positions awaiting salary adjustments
  • Delete dormant employees from legacy systems.

 
Freeze HR/Payroll legacy systems for daily processing beginning at 6:00 p.m.
 
Note: Any changes made to the employee data after 6:00 p.m. will need to be entered in both the legacy system and SCEIS after go-live on September 3.
Monday, August 19 Data migration and conversion efforts begin.
 
DUE: All completed data collection spreadsheets except for the IT2013 Template.
Friday, August 30 DUE: Completed IT2013 Template for leave balance information.
Tuesday, September 3 SCEIS HR/Payroll System Go-Live: House of Representatives and Code of Laws and Legislative Council.
 
Ready Room activities resume and post-go-live Ready Room Action Plans are distributed.
 
DUE: Updated IT2013 Template for leave balance information for September 1.